Engineers at the West Virginia DOT have identified 3 viable sites for a new brid
ID: 1098277 • Letter: E
Question
Explanation / Answer
If a particular cost or benefit is expected to occur permanently, then it shall be termed as perpetuity.
Thus, the P.V. of the perpetuity is: [Expected Cost or Benefit] / [Interest Rate]
LOCATION-S
The annual maintenance cost is $150,000
Thus, the P.V. of annual maintenance cost = 150,000 / 6% = $2.5M
Initial Investment = $50M
Total P.V. of costs = $2.5M + $50M = $52.5M
The savings in user cost is $7.6M.
Thus, the P.V. of savings in user cost = 7.6M / 6% = $126.7M
Thus, Benefit-Cost ratio = P.V. of Benefits / P.V. of Costs
= 126.7M / 52.5M
= 2.4127
LOCATION-D
The annual maintenance cost is $130,000
Thus, the P.V. of annual maintenance cost = 130,000 / 6% = $2.17M
Initial Investment = $75M
Total P.V. of costs = $2.17M + $75M = $77.17M
The savings in user cost is $4.1M.
Thus, the P.V. of savings in user cost = 4.1M / 6% = $68.3M
Thus, Benefit-Cost ratio = P.V. of Benefits / P.V. of Costs
= 68.36M / 77.17M
= 0.8855
LOCATION-N
The annual maintenance cost is $140,000
Thus, the P.V. of annual maintenance cost = 140,000 / 6% = $2.33M
Initial Investment = $60M
Total P.V. of costs = $2.33M + $60M = $62.33M
The savings in user cost is $5.9M.
Thus, the P.V. of savings in user cost = 5.9M / 6% = $98.33M
Thus, Benefit-Cost ratio = P.V. of Benefits / P.V. of Costs
= 98.33M / 62.33M
= 1.5775
THUS, AS PER BENEFIT-COST RATIO LOCATION-S SHOULD BE CHOSEN.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.