Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Case Studies Old Oregon Wood Store In 2015, George Wright started the Old Oregon

ID: 1106566 • Letter: C

Question

Case Studies Old Oregon Wood Store

In 2015, George Wright started the Old Oregon Wood Store to manufacture Old Oregon tables. Each table is carefully constructed by hand using the highest-quality oak. Old Oregon tables can support more than 500 pounds, and since the start of the Old Oregon Wood Store, not one table has been returned because of faulty workmanship or structural problems. In addition to being rugged, each table is beautifully finished using a urethane varnish that George developed over 20 years of working with wood-finishing materials.

The manufacturing process consists of four steps: preparation, assembly, finishing, and packaging. Each step is performed by one person. In addition to overseeing the entire operation, George does all of the finishing. Tom Surowski performs the preparation step, which involves cutting and forming the basic components of the tables. Leon Davis is in charge of the assembly, and Cathy Stark performs the packaging.

Although each person is responsible for only one step in the manufacturing process, everyone can perform any one of the steps. It is George’s policy that occasionally everyone should complete several tables on his or her own without any help or assistance. A small competition is used to see who can complete an entire table in the least amount of time. George maintains average total and intermediate completion times.

The data are shown in Figure 15.7.

Preparation Assembly Finishing Packing

Tom 100 160 250 275

George 80 160 220 230

Leon 110 200 280 290

Cathy 120 190 290 315

Figure 15.7 Manufacturing Time in Minutes

It takes Cathy longer than the other employees to construct an Old Oregon table. In addition to being slower than the other employees, Cathy is also unhappy about her current responsibility of packaging, which leaves her idle most of the day. Her first preference is finishing, and her second preference is preparation.

In addition to quality, George is concerned with costs and efficiency. When one of the employees misses a day, it causes major scheduling problems. In some cases, George assigns another employee overtime to complete the necessary work. At other times, George simply waits until the employee returns to work to complete his or her step in the manufacturing process. Both solutions cause problems. Overtime is expensive, and waiting causes delays and sometimes stops the entire manufacturing process.

To overcome some of these problems, Randy Lane was hired. Randy’s major duties are to perform miscellaneous jobs and to help out if one of the employees is absent. George has given Randy training in all phases of the manufacturing process, and he is pleased with the speed at which Randy has been able to learn how to completely assemble Old Oregon tables.

Randy’s average total and intermediate completion times are given in Figure 15.8.

Preparation Assembly Finishing Packing

Randy 110 190 290 300

Figure 15.8 Randy’s Completion Times in Minutes

1. What is the fastest way to manufacture Old Oregon tables using the original crew? How many could be made per day?

2. Would production rates and quantities change significantly if George would allow Randy to perform one of the four functions and make one of the original crew the backup person?

3. What is the fastest time to manufacture a table with the original crew if Cathy is moved to either preparation or finishing?

4. Whoever performs the packaging function is severely under­utilized. Can you find a better way of utilizing the four- or five-person crew than either giving each a single job or allowing each to manufacture an entire table? How many tables could be manufactured per day with this scheme?

Explanation / Answer

Answer:

Given Information :

Owner : George Brown started the Old Oregon Wood Store to manufacture Old Oregon tables.

Each table is carefully constructed by hand using the highest quality oak.

Old Oregon tables can support more than 500 pounds, and since the start of the Old Oregon Wood Store, not one table has been returned because of faulty workmanship or structural problems.

In addition to being rugged, each table is beautifully finished using a urethane varnish that George developed over 20 years of working with wood-finished materials.

The manufacturing process consists of four steps:

preparation, assembly, finishing, and packaging.

One person performs each step.

In addition to overseeing the entire operation, George does all of the finishing.

Tom Surowski performs the preparation step, which involves cutting and forming the basic components of the tables.

Leon Davis is in charge of the assembly

Cathy Stark performs the packaging.

Although each person is responsible for only one step in the manufacturing process, everyone can perform any one of the steps.

It is George's policy that occasionally everyone should complete several tables on his or her own without any help or assistance.

A small competition is used to see who can complete an entire table in the least amount of time.

George maintains average total and intermediate completion times.

The data are shown in following table.

Table 1

Manufacturing Time in minutes

Tom

Preparation

100

Assembly

160

Finishing

250

Packaging

275

George

Preparation

80

Assembly

160

Finishing

220

Packaging

230

Leon

Preparation

110

Assembly

200

Finishing

Packaging

290

Cathy

Preparation

120

Assembly

190

Finishing

290

Packaging

315

Table 2

Manufacturing Time in minutes

Randy

Preparation

110

Assembly

190

Finishing

290

Packaging

300

Question# 1: What is the fastest way to manufacture Old Oregon tables using the original crew? How many could be made per day?

Answer :

Fastest way to manufacture table as per the original table .

Select the minimum timing as well as alignment of each process.

Table 3

Manufacturing Time in minutes

Tom

Assembly

160

George

Preparation

80

Leon

Packaging

290

Cathy

Finishing

290

Consider the 8 hours shift , in 8 hours shift there are 480 min.

The maximum time required for finishing is 290 min.

So 480 / 290 = 1.66 no

So if they take a over time of 100 min then 2 tables can be manufactured , but it seems difficult from cost point of view.

-----------------------------------------------------------------------------------

Question #2: Would production rates and quantities change significantly if George would allow Randy to perform one of the four functions and make one of the original crew the backup person?

Answer :

If we see above table no 3 & compare with Randy's fig which are mentioned in . , then Randy's fig. are more .So its of no use to use Randy as a replacement other wise production will be hampered & the costs will be increased.

Question #3: What is the fastest time to manufacture a table with the original crew if Cathy is moved to either preparation or finishing?

Answer :

Table 4

Manufacturing Time in minutes

Tom

Finishing

250

George

Packaging

230

Leon

Assembly

200

Cathy

Preparation

120

Consider the 8 hours shift , in 8 hours shift there are 480 min.

The maximum time required for finishing is 250 min in table 4 for operation finishing by TOM.

So 480 / 250 = 1.92 no

So if they take a over time of 20 min then 2 tables can be manufactured , Compare to table no 1 cost can be minimized & production will increased .

Question #4: Whoever performs the packaging function is severely underutilized. Can you find a better way of utilizing the four- or five-person crew than either giving each a single job or allowing each to manufacture an entire table? How many tables could be manufactured per day with this scheme?

Table 4

Manufacturing Time in minutes

Tom

Finishing

250

George

Packaging

230

Leon

Assembly

200

Cathy

Preparation

120

In above table if 5 th no man is added & if he helps to Finishing as well as Packaging then both timing can be come down to half level.Its not only useful to apply the 5 th no person to packaging because its of no use , the finishing is also having more time .

So new time will be

Table 5

Manufacturing Time in minutes

Tom

Finishing

125

George

Packaging

115

Leon

Assembly

200

Cathy

Preparation

120

5 th person

125

115

Consider the 8 hours shift , in 8 hours shift there are 480 min.

The maximum time required for Assembly is 200 min for Leon in table 5

So 480 / 200 = 2.4 no

So in this we productivity can be increased.

Table 1

Manufacturing Time in minutes

Tom

Preparation

100

Assembly

160

Finishing

250

Packaging

275

George

Preparation

80

Assembly

160

Finishing

220

Packaging

230

Leon

Preparation

110

Assembly

200

Finishing

Packaging

290

Cathy

Preparation

120

Assembly

190

Finishing

290

Packaging

315

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote