The four alternatives described below are being evaluated. If the alternatives a
ID: 1120285 • Letter: T
Question
The four alternatives described below are being evaluated. If the alternatives are independent and there is no budget limitation, which alternative(s) should be selected based on the B/C analysis?
Question 14 options:
Select only C
Select A and C
Select A, B, C, and D
Select only A
Select only C
Select A and C
Select A, B, C, and D
Select only A
Cost in BIC Ratio Alternative Millions($) Compared to DN Incremental B/C when compared with alternative 1.50 0.85 1.30 0.70 50 60 65 0.55 1.40 0.65 3.50 0.80 0.05Explanation / Answer
B/C analysis is based on benefit/cost ratio.
It is ratio of sum of present value of benefits to sum of present value of costs
Based on B/C analysis a project should be choosen only when B/C is greater than 1 as project benefits is outweighing its costs
In this case no budget constraint is there and all projects are independent so we will choose all projects with B/C value of greater than 1
We will look as the column where B/C ratio is given compared to DN as it is comparing with do nothing
B/C ratio of only project A and C is greater than zero. So we will consider both projects A and C
So the answer is option 'B' i.e option A and C
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.