following? item consists of which of the A) Move, setup, assembly or run times B

ID: 1128198 • Letter: F

Question

following? item consists of which of the A) Move, setup, assembly or run times B) Plan, do, check, act or finish cycle. C) Plan, initiate, monitor, close or end cycle. D) Move, organize, assembly or run length. 9) Which of the following best describes a gross material requirements plan? A) A chart illustrating whether capacity has been exceeded. B) A table that corrects scheduled quantities for inventory on hand C) A schedule showing which products are to be manufactured and in what quantities. D) A schedule that shows total demand for an item, and when it must be ordered from or when production must be started. 10) Safety stock may be prudent when: A) Purchasing is overloaded with purchase orders B) Lead times may not be perfect C) Outsourcing or offshoring is used D) Master Production Schedule is errant 11) In the context of MRP Dynamics, a central strength of MRP systems is: A) Timely and accurate planning. B) Timely and accurate processing. C) Timely and accurate process improvement. D) Timely and accurate replanning. 12) Which of the following lot-sizing techniques results in the lowest holding costs? A) Lot-for-lot B) EOQ C) POQ. D) Lot-sizing. 13) MRP II also is known as: A) Manufacturer's Resource Planning B) Manufacturer's Resource Planning II. C) Major Requirements Planning D) Master Requirements Planning II. 14) Which of the following is FALSE about a closed-loop MRP system? A) Smoothing a resource requirements profile to stay within capacity limits may costs. B) Operations splitting sends pieces to the next operation before the entire lot the previous operation. C) Closed-loop MRP systems allow production planners to move work betwee smooth the load or to at least bring it within capacity Clonnd Ioon MRR cuetems do nnt add canacity, but rather seeks effective

Explanation / Answer

Ans:

8) Option A

move , setup ,assembly or run times.

Lead time is the total time required to manufacture a item and it includes order preparation time, queue time, setup time, run time, move time, inspection time.

9) Option D

a schedule that shows total demand for an item, and when it must be ordered from a supplier orwhen production must be started

Gross material requirement plan contains information about the total demand and material required to meet the demand. when order for materials should be placed and production should be started.

10) Option B

Lead times may not be perfect

When bills of material , inventory records and lead times are not perfect in such case some consideration of safety stock may be prudent.