One method for developing a mine containing an estimated 100,000 tons of ore will result in the recovery of 60% of the available ore deposit and will cost $23 per ton of material removed. A second method of development will recover only 53% of the ore deposit, but it will cost only $15 per ton of material removed. Subsequent processing of the removed ore recovers 300 pounds of metal from each ton of processed ore and costs $45 per ton of ore processed. The recovered metal can be sold for $0.84 per pound. You can sell all the metal that is recovered. Which method for developing the mine should be used if your objective is to maximize total profit from the mine? The profit from the mine using the first method is S(Round to the nearest dollar.)Explanation / Answer
First method:
Recovered Ore = 60% of 100,000 = 0.60*100,000 =60,000tons
Removal cost = 60,000*($23) = $1,380,000
Processing cost = 60,000*($45) = $ 2,700,000
Recovered metal = (300 lbs/ton)*60,000 tons = 18,000,000 lbs
Revenue = 18,000,000* $0.84 = $15,120,000
Profit = Revenue - Cost
Profit = 15,120,000 - 1,380,000 - 2,700,000 = $11,040,000.
So profit from the mine using first method is $11,040,000
For second method:
Recovered Ore = 53% of 100,000 = 0.53*100,000 =53,000tons
Removal cost = 53,000*($15) = $795,000
Processing cost = 53,000*($45) = $ 2,385,000
Recovered metal = (300 lbs/ton)*53,000 tons = 15,900,000 lbs
Revenue = 15,900,000* $0.84 = $13,356,000
Profit = Revenue - Cost
Profit = 13,356,000 - 795,000 - 2,385,000 = $10,176,000.
So profit from the mine using first method is $10,176,000
So Method 1 should be used for developing the mine if we want to maximize total profit from the mine because profit from method 1 is greater than profit from method 2