The structural engineering design section within the engineering department of a
ID: 1156692 • Letter: T
Question
The structural engineering design section within the engineering department of a regional electrical utility corporation has developed several standard designs for a group of similar transmission line towers. The detailed design for each tower is based on one of the standard designs. A transmission line project involving 48 towers has been approved. The estimated number of engineering hours needed to accomplish the first detailed tower design is 122. Assuming a 97% learning curve. a. What is your estimate of the number of engineering hours needed to design the sixth tower and to design the last tower in the project? b. What is your estimate of the cumulative average hours required for the first four designs? a. The number of engineering hours needed to design the sixth tower is hours. (Round to one decimal place.)Explanation / Answer
Tn=T1(N^b)
T1=122, b=log0.97/log2 , N=6
Tn=122(6^-0.04)=113.56 hours
for 48th tower
T48=122(48^(-0.04))=104.5 hours
CUmulative time
T1+T2+T3+T4=122(1)+122(2^(-0.4))+122(3^(-0.04))+122(4^(-0.04))=446.63 hours
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.