4. (15 points) A city wastewater treatment plant is working on a project to recl
ID: 1159443 • Letter: 4
Question
4. (15 points) A city wastewater treatment plant is working on a project to reclaim energy from waste methane generated by the plant's anaerobic digester. The project cost is anticipated at $1,050,000. The digester will cost $25,000 per year to operate. The digester will require major rebuilding at year 10 and year 20 at a cost of $100,000 per rebuild. The project will generate energy cost savings to the plant of S165,000 per year. The project life is 30 years; there is no significant salvage value at project end. Use CONVENTIONAL BENEFIT-COST ANALYSIS to determine whether the project is worth pursuing. Use a MARR of 15%.Explanation / Answer
The initial cost of digester is $1,050,000
Per year operational cost = $25,000
Rebuilding cost after 10 years = $100,000
Rebuilding cost after 20 years = $100,000
Project life = 10 years
MARR = 15%
Calculate the present worth of the cost of digester -
PW = $1,050,000 + $25,000(P/A, 15%, 30) + $100,000(P/F, 15%, 10) + $100,000(P/F, 15%, 20)
PW = $1,050,000 + ($25,000 * 6.5660) + ($100,000 * 0.2472) + ($100,000 * 0.0611)
PW = $1,050,000 + $164,150 + $24,720 + $6,110
PW = $1,244,980
The present worth of the cost of digester is $1,244,980
Per year saving from digester = $165,000
Project life = 10 years
MARR = 15%
Calculate the present worth of benefits of the digester -
PW = $165,000 (P/A, 15%, 30)
PW = $165,000 * 6.5660
PW = $1,083,390
The present worth of the benefit of the digester is $1,083,390
Calculate the conventional benefit-cost ratio -
Conventional B-C ratio = PW of benefits/PW of cost
Conventional B-C ratio = $1,083,390/$1,244,980 = 0.87
The conventional Benefit/Cost ratio of project is 0.87
The value of conventional B/C ratio have to be equal to or greater than 1 to make the project worth pursuing.
The conventional B/C ratio of digester is 0.87 which is less than 1.
So,
The project is not worth pursuing.