Three mutually exclusive alternatives are being considered. A B C First Cost $1,
ID: 1177189 • Letter: T
Question
Three mutually exclusive alternatives are being considered.
A B C
First Cost $1,000 $2,000 $3,000
Annual benefit 150 150 0
salvage value 1000 2700 5600
useful life,years 5 6 7
when each project reached the end of its life it would be sold for its salvage value and there would be no replacement.
A) construct a choice table for interest rates from 0%to 100%
B) if 8% is desired rate of return which project should be selected?
Explanation / Answer
1. for project A
total benefit after 5 years 150 *5 = 750 in 5 years
% return per year = 150 *100/1000 =15%
for project B
total profit = 150*6 =900
salvage value benefit = 700 ;
total= 1600 in 6 years ;
% return per year = 1600*100/(6*2000) =13.33%;
for project C
benefit after 7 years = 2600;
% return per year = 2600*100/7*3000 = 12.3 %;
2. for desired 8% rate
project A has the highets rate of return so PROJECT A should be selected
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.