The state of Nebraska has identified three viable sites for a new bridge. The costs associated with each bridge are shown. At an interest rate of 8% per year, determine which location is preferred, assuming the bridges will be permanent.
A B C
construction costs,$ 50,000,000 75,000,000 60,000,000
Maintenance Cost,$ 150,000 130,000 140,000
Benefits, $ 7,600,000 4,100,000 5,900,000
Explanation / Answer
A location is best suitable