Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME
ID: 1201788 • Letter: S
Question
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A — 3
B A 5
C A 4
D B 2
E C D 3
F D 1
G F 1
H E G 4
b. What is the critical path?
A-C-E-H
A-C-E-F-G-H
A-B-D-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
C 3 weeks F, 1 week G 1 week.
B3 weeks, D 2 weeks, E 4 weeks.
A 1 week, B 2 weeks, D 4 weeks.
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A — 3
B A 5
C A 4
D B 2
E C D 3
F D 1
G F 1
H E G 4
b. What is the critical path?
A-C-E-H
A-C-E-F-G-H
A-B-D-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
C 3 weeks F, 1 week G 1 week.
B3 weeks, D 2 weeks, E 4 weeks.
A 1 week, B 2 weeks, D 4 weeks.
Explanation / Answer
b. the project critical path is= A-B-D-E-H
c. project duration is 14 weeks
d. B3 weeks, D 2 weeks and E 4 weeks