4 As a project manager you should always be closely managing (circle all that ap
ID: 1206338 • Letter: 4
Question
4 As a project manager you should always be closely managing (circle all that apply):
a) Project schedule (projected start-up date)
b) Whether the project design will work as outlined in the SOW
c) Projected cost of the project
d) Mental models
e) None of the above
5) The “change management process” is a process whereby design changes are authorized and also communicated to the rest of the organization:
True False
6) A make-or-buy decision for a project is the decision to either do the work internally or contract it out to a third party ?
True False
7) To help decide whether you should outsource something to contractor (make or buy decision) you need to recognize there is an element of strategy (what your firm is choosing to focus on) and whether you would prefer to have that capability inside the company :
True False
Explanation / Answer
4.A
5. TRUE
6. TRUE
7. FALSE
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.