Could someone post the solution for each part please Your company is considering

ID: 1209595 • Letter: C

Question

Could someone post the solution for each part please

Your company is considering the following two investments for needed repairs on their building: initial Investment Years Maintenance Refurbishment Alternative 1 $500,000 10 $4,000 $50,000 Alternative 2 $450,000 10 $4,500 $90,00 MARR = 15% Refurbishment is made at end of 10 years so that they can sell the building. They want to make a single sum deposit at the beginning of the investment to pay for it. Which is the preferred alternative? Alternative 1 Alternative 2 Alternative 1 and Alternative 2 are the same The Do Nothing Alternative What is the value of that alternative $0 $625,203 $659,505 $683,108

Explanation / Answer

8) As we see from table abobe alternative 2 is better

PV = A/(1+MARR)^n where n is years

Alternative A MARR=0.15 Alternative B MARR=0.15 Year Initial investment Maintenance Refurbishment Total Total PV of Total Year Initial investment Maintenance Refurbishment Total Total PV of Total 0 500000 500000 500000 0 450000 450000 450000 1 4000 4000 3478 1 4500 4500 3913 2 4000 4000 3025 2 4500 4500 3403 3 4000 4000 2630 3 4500 4500 2959 4 4000 4000 2287 4 4500 4500 2573 5 4000 4000 1989 5 4500 4500 2237 6 4000 4000 1729 6 4500 4500 1945 7 4000 4000 1504 7 4500 4500 1692 8 4000 4000 1308 8 4500 4500 1471 9 4000 4000 1137 9 4500 4500 1279 10 4000 50000 54000 13348 10 4500 90000 94500 23359 532434 494831