A company manufactures a line of printers on a produce-to-order basis. Eachprint
ID: 1224525 • Letter: A
Question
A company manufactures a line of printers on a produce-to-order basis. Eachprinter requires an average of 30 labor-hours, and the manufacturing plant usesa backlog of orders to allow a level capacity aggregate plan. This plan provides aweekly capacity of 9,000 labor-hours. The company has prepared this five-week MPS: SEE TABLE BELOW
ANSWER THREE QUESTIONS, SHOW ALL WORK/FORMULAS
a. Compute the actual labor-hours required at the plant in each week andfor the total five weeks to produce the MPS (load). Compare the load tothe labor-hours capacity in each week and for the total five weeks (rough-cut capacity planning).
b. Does enough production capacity exist to produce the MPS?
c. What changes in the MPS would you recommend?
Weekly production 1 2 3 4 5 Printers 200 275 275 300 360Explanation / Answer
The rough cut capacity analysis is given below.
Weekly production Total 1 2 3 4 5 Printers 200 275 275 300 360 1410 Load 6000 8250 8250 9000 10800 42300 Capacity 9000 9000 9000 9000 9000 45000 Under/Over Load 3000 750 750 0 -1800 2700 The plant is underloaded in the first 3 weeks (primarily week 1) and it is overloaded in the last 2 weeks of the schedule. – Some of the production scheduled for week 4 and 5 should be moved to week 1.Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.