The state highway department is considering six routes for a new highway. Listed
ID: 1235951 • Letter: T
Question
The state highway department is considering six routes for a new highway. Listed below are the estimated construction costs, maintenance costs, and the user cost associated with each route.Route Construction Costs Annual Maintenance Costs Annual User Cost
A1 $1,100,000 $44,775 $540,000
A2 1,327,500 38,130 527,250
A3 1,525,000 33,500 517,000
A4 1,915,000 31,875 490,250
A5 2,125,000 28,500 460,500
A6 2,217,500 26,259 444,000
All costs are given per kilometer. The life of the highway is expected to be 30 years with no salvage value. If the interest rate is 8%, which route is most attractive?
a. Solve using incremental analysis
b. Solve using total investment analysis
c. If the estimated costs are in constant dollars, and the annual inflation rate is 8%, which route is favored?
Explanation / Answer
A. route A2is better B. route A3 isbetter C.route A6 is favoured
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.