construction project managment:
QUESTION 6
Quality, when referring to item installation, is not related to price.
True
False
3 points
QUESTION 7
Quality control normally refers to a plan to achieve quality, and quality assurance refers to inspection, testing, and necessary remediation.
True
False
3 points
QUESTION 8
If a project is built in a compressed time frame and quality work is maintained, then the cost of the project will decrease.
True
False
3 points
QUESTION 9
Duration, in most schedules, is expressed in working days, not calendar days.
True
False
3 points
QUESTION 10
Commercial cost databases do not accurately reflect a particular contractor’s costs.
True
False
Explanation / Answer
6) False . Better the quality, higher the price
7)True . By defintion of the terms
8)True. This is because the total man hour and machine running cost will reduce
9)True. This is is the normal convention followed
10)True. A particular contarctor's cost depends on various factors