construction project managment: QUESTION 16 The traditional contract project del
ID: 1711055 • Letter: C
Question
construction project managment:
QUESTION 16
The traditional contract project delivery system has three primary contractual parties: the owner, the architect, and the ____.
designer
contractor
consultant
engineer
QUESTION 17
Shop drawings, material data, and samples generally are referred to as ____.
indications
submittals
specifications
schedules
QUESTION 18
The ____ is ultimately responsible for the design of the facility to meet occupancy needs and must ensure that the products being installed are suitable to meet these needs.
contractor
architect
designer
fabricator
QUESTION 19
At all sites, toilet facilities shall be located within ____ feet, horizontally, of all employees
100
200
300
400
QUESTION 20
____ are held for larger projects to coordinate different areas of work.
Negotiations
Specialized reviews
Partnering meetings
Construction staff meetings
Explanation / Answer
Q16)
The three contractual parties are owner,architect and contractor,
Hence option 2 is correct.
Q17)
Material data, drawings these are all related to specifications of work.
Hence, spections is the correct choice.
Q 18)
The designer is responsible for all the design aspects of the work.
Hence desinger will be the correct answer.
Q19)
200 feet.
As per chegg guidelines only 4 parts should be answered in a question.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.