You have been assigned a new building project to manage. It was awarded based on
ID: 1711847 • Letter: Y
Question
You have been assigned a new building project to manage. It was awarded based on the Traditional Method. You were not involved in the bidding stage, but now it is your responsibility to manage this project and therefore you need to start awarding sub-bids to your subcontractors and material suppliers. After you reviewed the Construction Documents, you determined that the Architect required Shop Drawings for his approval for the following items - Reinforcing re-bars for all footings and foundations - Steel Framing of the building - Roof Trusses - All metal Doors with Steel Frames - Aluminum Storefront Glazing - Cabinets and counter tops. According to the Construction Schedule that was given to you for this Project, you determined the following: Start @ begining of day Duration 10/02 3 Days 10/05 4 Days 10/11 5 Days 10/18 1 day 10/19 2 days 10/23 5 days 10/30 4 days 11/03 3 days 11/8 3 days 12/21 3 days Finish @end of day 10/04 10/10 Foundation Excavation Concrete Footings&Pads; CMU Foundation walls Backfilling & grading Slab on Grade Steel Framing Roof Framing Metal Studs Wall Framing Exterior Doors & windows Cabinets and Counter tops 10/18 10/20 10/27 11/07 12/26 The Architect stated in the Construction Documents that he will need 1 week (5 working days) approval time (turnaround time) for any submittal. You need 1 day to process any paper work or to review any document The suppliers/subcontractors stated on their proposals/bids the following time line Manufacture& Ship 3 days 2 weeks 2 weeks 2 weeks 2 weeks 4 weeks Prepare Submittals 2 days Supplier/Sub Re-bar supplier Structural Steel Supplier Truss Company Door Supplier Aluminum/Glass Co. Cabinets Co. 4 days 2 days 2 weeks 3 daysExplanation / Answer
Rebar supplier - no latter than 09-28-17
Stuructural steel supplier - no latter than 09-29-17
Truss company - no latter than 10-10-17
Door supplier - no latter than 10-23-17
Aluminium/glass - no latter than 10-11-17
cabinets - no latter than 11-16- 17
S.No supplier manufacture and ship total work days needed date Last order date 1 Rebar 10/2 5 10/05 09-28-17 2 Stuructural steel 10/09 15 10/23 09-29-17 3 Truss 10/16 14 10/30 10-10-17 4 Door 10/28 12 11/08 10-23-17 5 Aluminium/glass 10/28 20 11/08 10-11-17 6 cabinets 11/21 23 12/20 11-16- 17Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.