tl: Mark True or False and et stmcets 1. In coestruction fails to True Fa 2. Det
ID: 1712625 • Letter: T
Question
tl: Mark True or False and et stmcets 1. In coestruction fails to True Fa 2. Detailed cost estimates "re prepared by the i- during the detailed design nge o ty Trae 3. The costs of mobilization and demobilization of of the cost of operating the equipment 4. The re-measared type of contracts 5. In cost-plas type of a piece of equipent ane considered True is mone risky to the contraclor from the lump smty False t True contracts, the sliding foe is a fee that decreases lincarly with the anoun Tnae t of cost savings made. False 6. It is to use hamp-sum contracts when the work is defined in detail and the risk True False 7. In the ng process, during the evaluation and selection stage, the owner is v responsible to inform all bidders of questions from contractors. competitive biddi a any changes in dates or regulations and answer any False If the project manager has the option to sclect between two methods of construction (working for 8 hours a day or for 12 hours a day), it is expected that the total direct cost of working for 12 hours a day to be lower while the duration is higher as compared with working for 8 hours a day Truc 8. False True 9. It is appropriate to use negotiated cost-plus contracts when the project is complex and the level of risk is low False True 10. Performing a work breakdown structure involves breaking down the project into definable and measurable work tasks, subtasks, and work packages. True FalseExplanation / Answer
1. True
2. False: the construction project cost is estimated by the client besides the choices made by project manager while drawing up the design brief
3. true
4. true
5. true
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.