Question

If a contractor is required to do change order work and the contractor and project owner cannot agree to the price, the contractor should

a)

attempt to get in writing from the owner that it is change order work

b)

agree to do the work under force account

c)

segment the cost of doing the work with a new job cost code

d)

all of these

a)

attempt to get in writing from the owner that it is change order work

b)

agree to do the work under force account

c)

segment the cost of doing the work with a new job cost code

d)

all of these

Explanation / Answer

Ans C

i.e contractor should segment the cost of doing the work with a new job cost code