QUESTION 38 The primary effect of the Davis Bacon requirements on a project will
ID: 1714598 • Letter: Q
Question
QUESTION 38 The primary effect of the Davis Bacon requirements on a project will be the stipulation that workers be paid the prevailing wage rates O True False QUESTION 39 Which of the following terms is defined as"changes or accumulations of changes that so greatly exceed the scope of the contract as to create a material breach of contracr? Change order Differing site conditions Cardinal changes Constructive changes QUESTION 40 An agency shop is one in which workers need not join the union, but they must pay the union dues FaseExplanation / Answer
38, as per Davis bacon act, The contractor’s mus pay at least the prevailing wage listed in the contract wage determination can be met by paying each worker,
prevailing wage comprises of basic hourly rate and any fringe benefits.
39 .A cardinal change is considered a material breach of the contract.
40, Ture ,
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.