Which of the following is the correct chronological order of the five phases that cover all aspects of a cabling project?

Presale/Sales; Rough-in; Trim-out; Testing, troubleshooting & certification; Customer support

Presale/Sales; Rough-in; Testing, troubleshooting & certification; Trim-out; Customer support

Presale/Sales; Customer support; Rough-in; Trim-out; Testing, troubleshooting & certification

Presale/Sales; Trim-out; Rough-in; Testing, troubleshooting & certification; Customer support

1.

Presale/Sales; Rough-in; Trim-out; Testing, troubleshooting & certification; Customer support

2.

Presale/Sales; Rough-in; Testing, troubleshooting & certification; Trim-out; Customer support

3.

Presale/Sales; Customer support; Rough-in; Trim-out; Testing, troubleshooting & certification

4.

Presale/Sales; Trim-out; Rough-in; Testing, troubleshooting & certification; Customer support

Explanation / Answer

The option with the correct chronological order is the number 1:

Presale/Sales; Rough-in; Trim-out; Testing, troubleshooting & certification; Customer support.