The following table shows the activities their optimistic, most likely and pessi
ID: 1844176 • Letter: T
Question
The following table shows the activities their optimistic, most likely and pessimistic durations and their immediate predecessors
Activity a m b Immediate Predecessors
A 4 8 12 ---
B 4 10 13 A
C 7 14 18 B
D 9 16 20 B
E 6 9 12 B
F 2 4 6 D,E
G 4 7 13 C,F
H 3 5 7 G
I 2 3 4 G,H
A- Determine the expected times and variances for each activity
B- Construct a project network for this problem
C- What is the probability that the project will be finished in less than 57 days?
D- What is the probability that the project will need at least 50 days?
Explanation / Answer
Expected time and varience for activiy A
a = 4 m =8 b =12
Expected time = (a+4m+b)/6 = (4+4*8+12)/6 = 8
Varience = (b-a)/6 = (12-4)/6 = 1.33
Total project duration,
0.33333
Taking all this values in network diagram,
critical path will be,
A-B-C-G-H-I
Project Duration = 8+9.5+13.5+7.5+5+3 = 46.5
Varience of project = sqrt(Va^2 + Vb^2 + Vc^2 + Vg^2 + Vh^2 + Vi^2)
V = sqrt(10.19)
V = 3.19
P(x<57) = P(z< (57-46.5)/3.19 )
P(x<57) = P(z< 3.29)
P(x<57) = 0.9995
P(x>50) = 1 - P(x<50)
P(x>50) = 1 - P(z<(50-46.5)/3.19)
P(x>50) = 1 - P(z<1.09)
P(x>50) = 1 - 0.8621
P(x>50) = 0.1379
a m b E V A 4 8 12 8 1.33333 B 4 10 13 9.5 1.5 C 7 14 18 13.5 1.83333 D 9 16 12 14.16667 0.5 E 6 9 12 9 1 F 2 4 6 4 0.66667 G 4 7 13 7.5 1.5 H 3 5 7 5 0.66667 I 2 3 4 30.33333
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.