1-exception oriented means ignore the things that are going as plans and pay att
ID: 1866869 • Letter: 1
Question
1-exception oriented means ignore the things that are going as plans and pay attention to the things are not going according to plan
true or false
3- scheduling materials deliveries to project is not that critical since a contractor can always go down to home depot and immediately buy necessary materials
true or false
7- most project managers and superintendents break a project down into specific elements and tasks as a normal part of their managerial technique
true or false
12- which of the following is not a goal of project calculation procedure?
a-determining the scheduled start and finish time for each activity
b-determining the float time for each activity
c- determining the critical activities for the project
d- determining the effect of weather on each activity
16- which of the following is not task that must be performed in order to provide a useful schedule information?
a- selection of subsets of information
b- sorting information into meaningful order
c- color coding the information according to standard practice
d- summarizing information when necessary
17- selection, sorting and summation are all important tasks for creating good schedule display ,but it is never necessary to do more than one task in any single display
TRUE OR FALSE
18- using WBS has become one of the most common ways of organizing schedule, in a part because most software system already include WBS tool
TRUE OR FALSE
19- one major advantage of WBS is that concept works very well with the concept of level of detail which is used for creating an activity lists
TRUE OR FALSE
20- a schedule can include either wbs or coding scheme such as project phase , but cannot include both
true or false
21- which f the following is NOT something that scheduler would need to know as he develops a project schedule
a- physical limits of the site
b- the public relations plans for the project
c- contractually required construction procedure
d- size and scope of the project
e- contract time allowed
Explanation / Answer
1. false
3. false
7. true
12. d
16. c
17. true
18. true
19. true
20. false
21. d