Question 37 1 pts When talking about \"resource utilization\" one commonly means

ID: 1866917 • Letter: Q

Question

Question 37 1 pts When talking about "resource utilization" one commonly means.. People, financing, equipment, and supplies Material resources Human resources People, equipment, and supplies Question 38 1 pts Is lack of resources on this particular activity having an adverse effect on the duration of the whole project, then Such an activity is likely to be larger than average Such an activity is likely to be late in the project Such an activity is likely to be on the critical path Such an activity is likely to involve software Question 39 1 pts The early-start and late-finish envelopes around the base plan show... The range of all possible expenditure plans for a project The error bounds on the base plan The range of possible plans as a function of resource levels The error bounds on project schedule

Explanation / Answer

37.people, financing, equipment and supplies

38.such an activity is likely to be on critical path.

Because if an critical activity is delayed then the duration of the project is also delayed.

39.The range of possible plans as a function of resource levels

40.There is probably a mistake because float should be zero for critical activities.

41.The data given are insufficient.

42.None of the above because before the discovery of the mount everest the highest mountain is Kangchenjunga.