The Ivanpah solar thermal power plant cost $2.2 billion to build. The gross plan
ID: 2088794 • Letter: T
Question
The Ivanpah solar thermal power plant cost $2.2 billion to build. The gross plant electric output is 392 MW, and the net output is 377 MW. The planned capacity factor was 27.4%, but the actual capacity factor in 2016 was 20.5%. At best the plant thermal efficiency appears to be 18%. In addition, for the daily startup process, the solar plant also burned 1.3x1012 Btu of natural gas in 2016. The cost of natural gas in 2016 was about $2.5 per million Btu. Assuming a levelized annual fixed charge rate of 7%, determine (a) the capital cost (c/kWh) and (b) the fuel cost (e/k Wh) for the electricity in 2016.Explanation / Answer
Given
Solar thermal power plant cost $2.2 billion
Electric output- 392 MW
Net output Capacity- 377MW
Capacity Factor- 27.4%
Actual capacity Factor-20.5%
Thermal effeciency- 18%
Solar fuel burned- 1.3x10^2 BTU of natural gas
Cost of natural gas 2016- $2.4/million
Annual fixed Charge- 7%
To find
A. Capacity cost
B. Fuel cost
Solution:
Net output capacity= 377MW
Average generation/day- 377x24x0.274(capacity factor)
-2479.152 mwh/day
Capital cost-
Fuel cost- 1.3x10^2 X $2.5
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.