U/ EE 300W The Design Process Name: Spring 2017 Test 1 Lab Section: - During the

ID: 2248522 • Letter: U

Question

U/ EE 300W The Design Process Name: Spring 2017 Test 1 Lab Section: - During the preliminary design phase, an engineer should write requirements for the project that conform to the S.M.A.R.T. standard What does the S.M.A.R.T.acronym stand for? (1 pt each, max 3 pts) c. M: A: R: T: (3 pts) At a CDR, a systems engineer presented a set of requirements to the review panel. she also delivered the results of a símulation that she said validated the requirements. What did she mean by this? e. The review panel responded to a certain CDR with an.action item that found fault with the verification test results. i. (2 pts) How should the presenting team handle an oction item? i. (2 pts) What is the function of verification tests? Technical communication 4. (3 pts) Technical communication (pick one): Ans.: a)... is a quick way to convey the necessary details b).... lows from a compelling beginning to a logical conclusion c) is faceless and formal in expression d) is effective regardless of the audience. e) All of the above Ans.: 5. (3 pts) A status report a)...is a complete report of the history of a project b) ...is a detailed accounting of the process of development of a project c)... should describe the standing of the project as of the date of the report d) .. must include all the details encountered so far All of the above -Pts out of Pts on this page

Explanation / Answer

Answer:

Acronym S.M.A.R.T is related to setting of objectives. Setting of objective may relate to employee performance, project management etc. While setting the objective one should be very clear about the objectives to be chosen. SMART identifies some characteristics which an objective must have-

1. S - Specific - It should relate to a particular area.

2. M - Measurable - Objective should be measured.

3. A - Assignable - Objective should be assigned to a particular person.

4. R - Realistic - It should not be such that it can not be achieved.

5. T - Time related - Time framework should be mentioned for completion of objective.