Given the old existing ground elevations at each point of the gridded area shown
ID: 2312039 • Letter: G
Question
Given the old existing ground elevations at each point of the gridded area shown below, calculate the volume of imported material base on the current attached level survey
Problem 1. Given the old existing ground elevations at each point of the gridded area shown below, calculate the volume of imported material base on the current attached level survey Scale: 1 20' Xs29.oo X87.80 W6.7/w5. 70 A3 526.70 A1 525.70 1 inch for calibration X830.30 29.50 28.60 7.80 x32.10 × 29.50 VA8.10 531.30 NO. OF OLD ELEV CUT SQUARES NEW ELEV POINT BS HI FS (C (n BM A274.3 525.8 A1 A2 A3 A4 B1 B2 83 B4 C1 C2 C3 C4 6.8 7.2 7.3 7.5 6.6 6.8 6.8 7.3 7.3 7.0 6.9 7.0Explanation / Answer
Note:
Let me know if there is anything else.
Have a Great Day!
POINT BS HI FS NEW ELEV OLD EVEV CUT (c) NO. OF SQUARES (n) c x n BM A27 4.3 530.1 525.8 A1 6.8 523.3 529 -5.7 1 -5.7 A2 7.2 522.9 527.8 -4.9 2 -9.8 A3 7.3 522.8 526.7 -3.9 2 -7.8 A4 7.5 522.6 525.7 -3.1 1 -3.1 B1 6.6 523.5 530.3 -6.8 2 -13.6 B2 6.8 523.3 529.5 -6.2 4 -24.8 B3 6.8 523.3 528.6 -5.3 4 -21.2 B4 7.3 522.8 527.8 -5 2 -10 C1 7.3 522.8 532.1 -9.3 1 -9.3 C2 7 523.1 531.3 -8.2 2 -16.4 C3 6.9 523.2 529.5 -6.3 2 -12.6 C4 7 523.1 528.1 -5 1 -5 24 -139.3 Average cut/fill: : -139/24 -5.804166667 site area: (3x2) in2 0.0039 m2 Total cut -0.02263625 m3Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.