BIM Edecation Program Model Creation Sequence The following activities focus on
ID: 2312452 • Letter: B
Question
BIM Edecation Program Model Creation Sequence The following activities focus on some of the information needed to create a BIM Execution Plan. You will most likely need to refer to the materials covered in Sessions 1 and 2 to complete the activities. Scenario You are the project manager for a hospital that wants to add a 200,000 SE, eight- story expansion to the existing building. You are about to engage the design team. To ensure that the project can realize the benefits of BIM, you will be working under the ConsensusDocs BIM Addendum, which requires that a BIM Execution Plan be developed within 30 days. You want to include specific language in the contract with the design team. On your BIM project team: . The architect has considerable experience with Bentley Architecture. The structural engineer typically designs with Autodesk Revit Structure software. . The MEP consultant is experienced with AutoCAD MEP software. The MEP engineer estimates, based on past experience, that a model of the project designed with AutoCAD MEP software would exceed 150MB. The specialty contractor base in your area is well-versed in creating models for coordination The CM has not yet been selected for the project Task Develop a BIM Execution Plan that considers the experience of the project participants. Identify processes and opportunities for coordination, clash detectionExplanation / Answer
BIM Execution Plan-
Objectives
BIM Goals & Objectives
From Project Managers Perspective
Design visualization
Clash Coordination.
2. Energy Analysis
Will help in ensuring that no conflicts are encountered during execution thus saving time and money during construction
This is more of a sustainability checkpoint to ensure that the proposed design is within the targeted sustainability parameters.
Documentating from BIM platform
2.Detailed Cost Estimate
To ensure that design and construction informations is
consistent across all project drawings
It’s more of a check-point now to ensure that the design is within the budget.
As-built Model Development
To have an accurate as-built model along with as- built drawings serves the following objective-
In Use Stage
Linking of Facility Management Data with As-built BIM Models
Utilizing BIM for Facility Management
All the scattered information is now put together and brought at one-place. This brings in significant efficiencies in the overall facility management process.
To be done because owner is responsible for managing & operating the facility.
same as above
Process Map
Let us first see the scenario from capability perspective.
Stakeholder
BIM capability
Inferences
Architect
capable , worked on Bentley architecture & willing to take up BIM themselves
Their BIM part will be done by themselves,
Structural Engineer
capable & trained in Revit
Their BIM part will be done by themselves
MEP Engineer
BIM incapable, worked on AutoCad MEP Software
Needs to be trained on BIM
Contractor
likely to be BIM capable as per the creating models for coordination
Contractor can either be trained to utilize BIM if he is interested or can continue to work in the traditional way (i.e. without using BIM)
CM
Not yet on board/ Not selected yet
A BIM capable CM to be hired##
Energy Consultant
Not on board
A BIM capable consultant to be hired**
2.1Responsibility Matrix: Role of BIM Consultant
Stakeholder
BIM capability
Inferences
Proposed Role of BIM Consultancy Firm
Architect
capable & willing to take up BIM themselves
Their BIM part will be done by themselves
NA
Structural Engineer
capable , trained in Autodesk Revit & willing to take up BIM themselves
Their BIM part will be done by themselves
NA
MEP Engineer
BIM incapable
They can only work on a older an version of Autodesk's Autocad MEP Software
Training & Implementation Support
Stage of WorkBIM Goals & Objectives
From Project Managers Perspective
Reason Capturing of Existing Condition 3D laser scanning and developing of BIM models analysis of the current condition in the hospital ,it is very important to accurately capture the existing condition with the help of 3Dlaser scanning . Concept Design StageDesign visualization
Will provide good understanding of the project to the client Developed Design StageClash Coordination.
2. Energy Analysis
Will help in ensuring that no conflicts are encountered during execution thus saving time and money during construction
This is more of a sustainability checkpoint to ensure that the proposed design is within the targeted sustainability parameters.
Technical Design StageDocumentating from BIM platform
2.Detailed Cost Estimate
To ensure that design and construction informations is
consistent across all project drawings
It’s more of a check-point now to ensure that the design is within the budget.
Construction Design Stage 4D Simulation for Project Tracking 4D Simulation can be utilized for project progress tracking on a monthly basis or on a quarterly basis depending upon client’s requirement Handover & Close-out StageAs-built Model Development
As-built Drawing production (Optional)To have an accurate as-built model along with as- built drawings serves the following objective-
- Firstly, Authenticity of as-built drawings can be checked by performing visual and clash checks as it is much more easier to check a single model then hundreds of drawings
- Secondly, preparation of an as-built model gives client great flexibility to utilize BIM for Facility Management.
In Use Stage
Linking of Facility Management Data with As-built BIM Models
Utilizing BIM for Facility Management
All the scattered information is now put together and brought at one-place. This brings in significant efficiencies in the overall facility management process.
To be done because owner is responsible for managing & operating the facility.
same as above