Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the following alternative projects in the table below. Each project wou

ID: 2329783 • Letter: C

Question

Consider the following alternative projects in the table below. Each project would last for five years.

1) Find the NPV for each project at a 10% discount rate.

2) Find the profitability index for each project at a 10% discount rate.

3) What discount rate would make the NPV=0 (i.e. breakeven in time) for each project?

Use excel to populate the table below. Show all cell references, show all formulas used, and show all calculations clearly.

Project A

Project B

    Initial investment

$80,000

$60,000

    Annual net cash inflows

20,000

16,000

$5,000 in maintenance

Year 2

Year 3

    Salvage value

10,000

8,000

Project A

Project B

    Initial investment

$80,000

$60,000

    Annual net cash inflows

20,000

16,000

$5,000 in maintenance

Year 2

Year 3

    Salvage value

10,000

8,000

Explanation / Answer

Project A

Year

Cash Outflow

Cash Inflow

Net Cash Flow

Discounting factor at 10%

Discounted Cash flow

1

$ 20,000.00

$       20,000.00

0.909090909

$ 18,181.82

2

$     (5,000.00)

$ 20,000.00

$       15,000.00

0.826446281

$ 12,396.69

3

$ 20,000.00

$       20,000.00

0.751314801

$ 15,026.30

4

$ 20,000.00

$       20,000.00

0.683013455

$ 13,660.27

5

$ 20,000.00

$       20,000.00

0.620921323

$ 12,418.43

5

$ 10,000.00

$       10,000.00

0.620921323

$    6,209.21

Present value of Cash Flows

$ 77,892.72

Less: Initial Investment

$ 80,000.00

Net Present Value

$ (2,107.28)

Profitability Index (77892.72/80000)

       0.97

Project B

Year

Cash Outflow

Cash Inflow

Net Cash Flow

Discounting factor

Discounted Cash flow

1

$ 16,000.00

$       16,000.00

0.909090909

$ 14,545.45

2

$ 16,000.00

$       16,000.00

0.826446281

$ 13,223.14

3

$     (5,000.00)

$ 16,000.00

$       11,000.00

0.751314801

$    8,264.46

4

$ 16,000.00

$       16,000.00

0.683013455

$ 10,928.22

5

$ 16,000.00

$       16,000.00

0.620921323

$    9,934.74

5

$    8,000.00

$         8,000.00

0.620921323

$    4,967.37

Present value of Cash Flows

$ 61,863.38

Less: Initial Investment

$ 60,000.00

Net Present Value

$    1,863.38

Profitability Index (61863.38/60000)

        1.03

Requirement

Project A

Project B

NPV

$     (2,107.28)

$    1,863.38

NPV of project A is negative hence it is advisable to go with Project B

Requirement 2

Project A

Project B

Profitability Index

$                0.97

$            1.03

Profitability index of more than is considered beneficial hence Project B should be accepted.

Requirement 3

A rate at which NPV is equal to zero is IRR or Internal rate of Return.

Discount rate at which NPV is Zero.

Project A 9.04% Approx

Project B 11.14% Approx

Project A

Year

Cash Outflow

Cash Inflow

Net Cash Flow

Discounting factor at 109.04%

Discounted Cash flow

1

$ 20,000.00

$       20,000.00

0.917094644

$                      18,341.89

2

$     (5,000.00)

$ 20,000.00

$       15,000.00

0.841062586

$                      12,615.94

3

$ 20,000.00

$       20,000.00

0.771333993

$                      15,426.68

4

$ 20,000.00

$       20,000.00

0.707386274

$                      14,147.73

5

$ 20,000.00

$       20,000.00

0.648740163

$                      12,974.80

5

$ 10,000.00

$       10,000.00

0.648740163

$                        6,487.40

Present value of Cash Flows

$                      79,994.44

Less: Initial Investment

$                      80,000.00

Net Present Value

$                              (5.56)*

NPV of $ 5.56 is due to Round off.

Project B

Year

Cash Outflow

Cash Inflow

Net Cash Flow

Discounting factor

Discounted Cash flow

1

$ 16,000.00

$       16,000.00

0.899766061

$ 14,396.26

2

$ 16,000.00

$       16,000.00

0.809578964

$ 12,953.26

3

$     (5,000.00)

$ 16,000.00

$       11,000.00

0.728431676

$    8,012.75

4

$ 16,000.00

$       16,000.00

0.655418099

$ 10,486.69

5

$ 16,000.00

$       16,000.00

0.589722961

$    9,435.57

5

$    8,000.00

$         8,000.00

0.589722961

$    4,717.78

Present value of Cash Flows

$ 60,002.31

Less: Initial Investment

$ 60,000.00

Net Present Value

$            2.31

Profitability Index (61863.38/60000)

1.00**

NPV of $ 1 is due to Round off.

Project A

Year

Cash Outflow

Cash Inflow

Net Cash Flow

Discounting factor at 10%

Discounted Cash flow

1

$ 20,000.00

$       20,000.00

0.909090909

$ 18,181.82

2

$     (5,000.00)

$ 20,000.00

$       15,000.00

0.826446281

$ 12,396.69

3

$ 20,000.00

$       20,000.00

0.751314801

$ 15,026.30

4

$ 20,000.00

$       20,000.00

0.683013455

$ 13,660.27

5

$ 20,000.00

$       20,000.00

0.620921323

$ 12,418.43

5

$ 10,000.00

$       10,000.00

0.620921323

$    6,209.21

Present value of Cash Flows

$ 77,892.72

Less: Initial Investment

$ 80,000.00

Net Present Value

$ (2,107.28)

Profitability Index (77892.72/80000)

       0.97

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote