Gilchrist Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. At the beginning of the most recently completed year, the Corporation estimated the machine-hours for the upcoming year at 28,100 machine-hours. The estimated variable manufacturing overhead was $4.47 per machine-hour and the estimated total fixed manufacturing overhead was $789,048. The predetermined overhead rate for the recently completed year was closest to:
Explanation / Answer
Option A. $32.55 per machine-hour
1. Computation of predetermined overhead rate
Predetermined overhead rate = Estimated Variable Manufacutirng OH per Machine Hour + (Estimated Fixed Manufacturing OH / Estimated Machine Hour)
Predetermined overhead rate = $4.47 + ($789048 / 28100)
Predetermined overhead rate = $4.47 + $28.08
Predetermined overhead rate = $32.55 per Machine Hour