Which of the following mathematical equations is used to calculate a predetermined overhead rate?
a. Predetermined Overhead Rate = Estimated Annual Manufacturing Cost / Estimated Quarterly Activity Level
b. Predetermined Overhead Rate = Actual Annual Cost of Goods Sold / Estimated Semi-annual Labor Hours
c. Predetermined Overhead Rate = Estimated Annual Overhead / Actual Annual Activity Level
d. Predetermined Overhead Rate = Actual Annual Overhead / Actual Annual Activity Level
e. Predetermined Overhead Rate = Estimated Annual Overhead / Estimated Annual Activity Level
Explanation / Answer
Answer:
e. Predetermined overhead rate = Estimated Annual Overhead / Estimated Annual Activity Level
All other options are incorrect formula