The following information is available regarding the total manufacturing overhea
ID: 2339674 • Letter: T
Question
The following information is available regarding the total manufacturing overhead of Bursa Mfg. Co. for a recent four-month period Machine-Manufacturing January February March April Hours 5,300 3,200 4,900 2,700 Overhead 300,000 224,000 263,800 180,000 a-1. Use the high-low method to determine the variable element of manufacturing overhead costs per machine-hour. (Round your answer to 2 decimal places.) a-2. Use the high-low method to determine the fixed element of monthly overhead cost. b. Bursa expects machine-hours in May to equal 5,300. Use the cost relationships determined in part a to forecast May's manufacturing overhead costs c. Suppose Bursa had used the cost relationships determined in part a to estimate the total manufacturing overhead expected for the months of February and March. By what amounts would Bursa have over- or underestimated these costs? Manufacturing overhead cost per machine hour Fixed element of monthly overhead cost 2 b. Estimated manufacturing overhead cost Amount c. February MarchExplanation / Answer
a-1. Manufacturing overheads cost = $ 46.15 per machine hour a-2. Fixed element of monthly overhead cost = $ 55,385 b. Estimated overhead cost = $ 3,00,000 c. February = $ 20,923 Underapplied March = $ 17,738 Overapplied Workings: Month Machine hours Manufacturing Overheads High Activity = January 5,300 $ 3,00,000 Low Activity = April 2,700 $ 1,80,000 Difference = 2,600 $ 1,20,000 a-1. Variable cost per unit = Difference in total cost / Difference in activity = ($1,20,000) / (2,600) = $ 46.15 per machine hour a-2. Fixed Cost = Total cost - (Variable cost per socks X Activity) = $3,00,000 - ($46.15 X 5,300) = $ 55,385 or = $1,80,000 - ($46.15 X2,700) = $ 55,385 b. Total manufacturing overheads cost for may = Fixed cost + Variable cost = $55,385 + ($46.15 XMachine hours) = $55,385 + ($46.15 X 5,300) = $ 3,00,000 c. February = 3,200 Machine hours Actual overheads applied = 2,24,000 Estimated overheads Total manufacturing overheads cost = Fixed cost + Variable cost = $55,385 + ($46.15 X3,200) = $ 2,03,077 Over/Under applied overheads = Actual overheads - Estimated overheads = $2,24,000 - $2,03,077 Under applied overheads = $ 20,923 March = 4,900 Machine hours Actual overheads applied = 2,63,800 Estimated overheads Total manufacturing overheads cost = Fixed cost + Variable cost = $55,385 + ($46.15 X4,900) = $ 2,81,538 Over/Under applied overheads = Actual overheads - Estimated overheads = $2,63,800 - $2,81,538 Over applied overheads = $ 17,738
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.