Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Sweeten Company had no jobs in progress at the beginning of March and no beginni

ID: 2341144 • Letter: S

Question

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. t started only two jobs during March-Job P and Job Q Job P was completed and sold by the end of the March and Job Q was incomplete at the end of the March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional infcrmation is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March Estimated total fowed manufacturing overhead10000 direct labor-hour Estimated total direct labor-hours to be worked Total actual manufacturing overhead costs incurred s12.500 21000500 1 125 points Required: What is the company's predetermined overhead rate? Relerences Book & Resources 03-05 Use -accounts t Leaming oive 03-02 Apply overhead cest toj ftin jb-dercing Difficulty 2 MediuLeamingie03-03 verage cost pr nt of a jo stal 3-01 Compute aUnderstnd the fow of costs ovenappled overhead cs and preae thejoualn 2. 15points How much manufacturing overhead was applied to Job P and Job Q?

Explanation / Answer

Solution:

1)

Predetermined Overhead Rate = Estimated variable manufacturing overhead per direct labor hour + Estimated Fixed Manufacturing Overhead Per direct labor hour

Estimated Fixed Manufacturing Overhead Per direct labor hour = Total Estimated Fixed MOH $10,000 / Total Estimated Direct Labor hour 2,000

= $5 per DLH

Predetermined Overhead Rate = $1.00 + $5.00 = $6 per direct labor hour

2)

Applied Manufacturing Overhead to Jobs

Job P

Job Q

Actual Direct labor hours worked (A)

1400

500

Overhead Rate per DLH (B)

$6

$6

Applied Manufacturing Overhead (A*B)

$8,400

$3,000

3)

Direct labor hourly wage rate

Job P

Job Q

Direct Labor Costs (A)

$21,000

$7,500

Actual Direct labor hours worked (B)

1400

500

Direct labor hourly wage rate (A/B)

$15.00

$15.00

4)

If Job P includes 20 units, then its unit product cost is

Job P

Direct Materials

$13,000

Direct Labor Costs

$21,000

Applied Manufacturing Overhead

$8,400

Total Manufacturing Costs

$42,400

Total Units

20 Units

Unit Product Cost ($42,400 / 20)

$2,120

5)

Total Manufacturing Cost assigned to Job Q

Job Q

Direct Materials

$8,000

Direct Labor Costs

$7,500

Applied Manufacturing Overhead

$3,000

Total Manufacturing Costs

$18,500

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Pls ask separate question for remaining parts

Job P

Job Q

Actual Direct labor hours worked (A)

1400

500

Overhead Rate per DLH (B)

$6

$6

Applied Manufacturing Overhead (A*B)

$8,400

$3,000