Machine Hours MFG Overhead Cost February 6,900 $6,250 March 5,000 $5,375 April 6
ID: 2344234 • Letter: M
Question
Machine Hours MFG Overhead Cost
February 6,900 $6,250
March 5,000 $5,375
April 6,300 $ 6,025
May 9,333 $ 7,975
June 6,833 $6,050
(a) Using the high-low method, compute the following:
(1) The variable element of overhead cost per machine-hour:
$____________________ per machine-hour
(2) The fixed element of monthly overhead cost: $__________________
(b) Use the cost relationship determined in part a to estimate the total manufacturing overhead costs for July 2010, given that 7,250 machine-hours are scheduled. $___________________
Explanation / Answer
(7975-5375)/(9333-5000)= .60 5375- .60*5000= 2375 Y= .60 x +2375 Y= .60*7250 +2375=6,725
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.