Additional information about the company follows: Hubs require $25 in direct mat
ID: 2346429 • Letter: A
Question
Additional information about the company follows: Hubs require $25 in direct materials per unit, and Sprockets require $18. The direct labor wage rate is $12 per hour. Hubs are more complex to manufacture than Sprockets and they require special processing The ABC system has the following activity cost pools: Compute the activity rate for each activity cost pool. (Omit the "$" sign in your response.) Determine the unit cost of each product according to the ABC system, including direct materials and direct labor. (Round your answers to 2 decimal places. Omit the "$" sign in your response.)Explanation / Answer
Requirement 1
Machine setups $21,600 / 180 = $120 per machine setup
Special processing $225,500 / 4,100 = $55 per processing
General factory $470,000 / 29,400 = $16
Requirement 1
Hubs Sprockets
Direct materials $25.00 $18.00
Direct labor $8.40 $3.60
Overhead $13.20 $4.97
Unit cost $46.60 $26.57
Machine setups $0.67 $0.17
Special process. $1.25 0
General factory $11.20 $4.80
$13.12 $4.97