Percy Resources Company acquired a tract of land containing an extractable natur
ID: 2347406 • Letter: P
Question
Percy Resources Company acquired a tract of land containing an extractable natural resource. Percy is required by its purchase contract to restore the land to a condition suitable for recreational use after it has extracted the natural resource. Geological surveys estimate that the recoverable reserves will be 2,000,000 tons, and that the land will have a value of $1,200,000 after restoration. Relevant cost information follows:Land
$9,000,000
Estimated restoration costs
1,800,000
If Percy maintains no inventories of extracted material, what should be the charge to depletion expense per ton of extracted material?
$5.40
$3.90
$4.50
$4.80
Explanation / Answer
If Percy maintains no inventories of extracted material, what should be the charge to depletion expense per ton of extracted material?
$5.40
$3.90
$4.50
$4.80
9,000,000 +1,800,000 ------1,200,000 / 2,000,000 tons = $4.80
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.