The Cutting Department of Groneman Manufacturing has the following production an
ID: 2348489 • Letter: T
Question
The Cutting Department of Groneman Manufacturing has the following production and cost data for July.Production
Costs
1. Transferred out 9,000 units. Beginning work in process $ -0-
2. Started 3,000 units that are 60% complete as Materials 45,000
to conversion costs and 100% complete as Labor 16,200
to materials at July 31. Manufacturing overhead 18,900
Materials are entered at the beginning of the process. Conversion costs are incurred uniformly during the process.
Determine the equivalent units of production for (1) materials and (2) conversion costs.
Compute unit costs and prepare a cost reconciliation schedule. (Round unit costs to 2 decimal places, e.g. 10.50. Use rounded amounts for future calculations. Round other answers to 0 decimal places, e.g. 125.)
Explanation / Answer
Total Material Costs = $45000
Total equivalence unit = 9000 + 3000 x 0.6 = 10800 EU
Cost per EU = 45000/10800 = $4.167
Total Conversion Costs = 16200 + 18900 = $35100
Total Equivalent units = 9000 + 3000 = 12000 EU
Cost per equivalent units = 35100 / 12000 = $2.925/EU
Total Cost for Finished Good = 9000 x 2.925 + 9000 x 4.167 = = 26325 + 37500 = $63825
Total Cost for Ending Work in Progress = 3000 x 2.925 + 3000 x 0.6 x 4.167 = 8775 + 7500 = $16275
COST PER UNIT OF FINISHED GOOD = 63825 /9000 = $7.09
Hope this helps!
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.