1) The following material standards have been established for a particular produ
ID: 2348864 • Letter: 1
Question
1) The following material standards have been established for a particular product: Standard quantity per unit of output... 6.8 Meters Standard Price...$14.40 per Meter
The following data pertain to operations concerning teh product for the last month:
Actual materials purchased... 4,400 meters
Actual cost of materials purchased... $60,500
Actual materials used in production...3,800 meters
Actual output...400 units
Q: What is the materials price variance for the month?
A:$14,850 U
B:$8,250 U
C:$8,640 U
D:$2,860 F
2) The following labor standards have been established for a particular product:
Standard labor-hours per unit of output... 5.0 hours
Standard labor rate... $19.85 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked... 7,300 hours
Actual total hours cost...$148,190
Actual output... $1,400 units
Q:What is the labor efficiency variance for the month?
A:$5955 U
B:$9240 U
C:$9240 F
D:$6090 U
Explanation / Answer
Standard cost is $14.40 per meter Actual cost was ($60,500 / 4,400 ) = $ 13.75 per meter, so the variance is favorable. Materials price variance = AQ * (AP - SP) = 4,400 * ($13.75 - $14.40) = 4,400 * ( - $ 0.65 ) = - $2,860 The material price variance was $2,860 F AQ = Actual quantity purchased AP = Actual price SP = Standard price