Hurley Corporation has identified the following overhead costs and cost drivers
ID: 2353180 • Letter: H
Question
Hurley Corporation has identified the following overhead costs and cost drivers for the coming year:Overhead item Cost Driver Budgeted Cost Budgeted Activity Level
Machine setup Number of setups $20,000 200
Inspection Number of inspections $130,000 6,500
Material handling Number of material moves $80,000 8,000
Engineering Engineering hours $50,000 1,000
$280,000
The following information was collected on three jobs that were completed during the year:
JOB 101 JOB 102 JOB 103
Direct material $5,000 $12,000 $8,000
Direct labor $2,000 $2,000 $4,000
Units completed 100 50 200
Number of setups 01 02 04
Number of inspections 20 10 30
Number of material moves 30 10 50
Engineering hours 10 50 10
Budgeted direct labor cost was $100,000, and budgeted direct material cost was $280,000.
a. If the company uses activity-based costing, how much overhead cost should be assigned to Job 101?
Explanation / Answer
If the company uses activity-based costing, how much overhead cost should be assigned to Job 101?
ANSWER:
Machine setup: $20000/200 x 1 = $100
Inspection: $130000/6500 x 20 = $400
Material handling: $80000/8000 x 30 = $300
Engineering: $50000/1000 x 10 = $500
Total Overhead cost = 100 + 400 + 300 + 500 = $1300
Hope this helps!
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.