Castner Corp is considering implementation of a JIT inventory system. The compan

ID: 2354581 • Letter: C

Question

Castner Corp is considering implementation of a JIT inventory system. The company's industrial engineer recently conducted a study to determine the average number of days spent in each activity of the production process. The following table summarize her findings:

Production Activity Number of days

Inspecting materials 3

Storing materials 17

Moving materials into production3

Setting up production equipment 2

Cutting materials6

Bending materials5

Assembling finished products 9

Painting finished products 5

A-Identify Castner's value-added production activities

B-Identify Castner's non value added production activities

C-Calculate Castner's total cycle time

D-Determine Castner's manufacturing efficiency ratio

E-Which of the above activities might be reduced or eliminated if Castner implemented a JIT system

F-What ethical issues might be related to eiminating some on the non value added activities

When working the problem, please show how you come up to the answer; this will greatly help me. Thank you

Explanation / Answer

(c)Castner's total cycle time = 3+17+ 3+2+ 6+5+9+5 = 50 daysd .Manufacturing efficiency ratio: Value-Added Time / Total Cycle TimeCastner