Type I. Zayner Company is a job-order costing firm that use activity based costi

ID: 2369615 • Letter: T

Question

Type

I.                     Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:<?xml:namespace prefix = o ns = "urn:schemas-microsoft-com:office:office" />

Activity                                           Cost                        Driver                Amount of Driver

Engineering design                    $120,000       Engineering Hours             3,000 hrs

Purchasing                                       80,000       Number of parts               10,000 parts

Other overhead                            250,000       Direct labor hours            40,000 hours

Zayner worked on five jobs in July. Data are as follows:

                                  Job #60             Job # 61         Job # 62               Job # 63          Job # 64

Balance, 7/1             $32,450          $40,770           $29,090                          $0                      $0

Direct materials       $26,000          $37,900           $25,350                 $11,000           $13,560

Direct labor              $40,000          $38,500           $43,000                  $20,900           $18,000

Engineering hours        20                     10                     15                             100                   200

Number of parts           150                   180                  200                            500                  300

Direct labor hours        2,500              2,400              2,600                        1,200               1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Required:

1.       Calculate the activity rates for each of the three overhead activities.

2.       Prepare job-order cost sheets for each job showing all costs through July 31.

3.       What is the cost of each job by the end of July?

I.                     Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:

Activity                                           Cost                        Driver                Amount of Driver

Engineering design                    $120,000       Engineering Hours             3,000 hrs

Purchasing                                       80,000       Number of parts               10,000 parts

Other overhead                            250,000       Direct labor hours            40,000 hours

Zayner worked on five jobs in July. Data are as follows:

                                  Job #60             Job # 61         Job # 62               Job # 63          Job # 64

Balance, 7/1             $32,450          $40,770           $29,090                          $0                      $0

Direct materials       $26,000          $37,900           $25,350                 $11,000           $13,560

Direct labor              $40,000          $38,500           $43,000                  $20,900           $18,000

Engineering hours        20                     10                     15                             100                   200

Number of parts           150                   180                  200                            500                  300

Direct labor hours        2,500              2,400              2,600                        1,200               1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Required:

1.       Calculate the activity rates for each of the three overhead activities.

2.       Prepare job-order cost sheets for each job showing all costs through July 31.

3.       What is the cost of each job by the end of July?

your question here

Explanation / Answer

https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&ved=0CDMQFjAA&url=http://www.isedi.it/repository/1281/Programmazione e controllo ESERCIZI Capitolo 4.pdf&ei=FiFYUeCjGoH-rAeP94GoDA&usg=AFQjCNGmVyjVx3DqO-7pOGBWHCueC9ugJQ&sig2=f0dqI8FSV2hBydWsKiGVBw&bvm=bv.44442042,d.bmk


the above link will help