The following information pertains to Yap Company's Grinding Department for the month of April:
All materials are added at the beginning of the process. Using the weighted-average method, the cost per equivalent unit for materials is closest to:
Units Materials Costs Beginning work in process 27,000 $23,500 Started in April 47,500 $33,000 Units completed and transferred out 55,500 Ending work in process 19,000Explanation / Answer
Hi,
Please find the answer as follows:
Cost per equivalent unit for materials = Total Material Cost/Total Units Complete and Transferred + Ending WIP)
= (23500 + 33000)/(55500 + 19000) = .758 or .76