The Overdale plant has two categories of overhead: maintenance and inspection. C
ID: 2371962 • Letter: T
Question
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:
Maintenance
£120,000
Inspection
£200,000
The plant currently applies overhead during direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:
Direct materials
£1,500
Direct labour
£5,000
Machine hours
400
Number of inspections
6
Direct labour hours
750
Using direct labour hours to assign overhead, the total cost of the potential job would be:
£9,500
£6,000
£3,000
£1,600
Maintenance
£120,000
Inspection
£200,000
Explanation / Answer
Total OH = 120000+200000 = 320000
Budeted DL Hrs = 80,000
S0 OH Rate based on DL = 320,000/80,000 = 4 per Hr
Total Job cost :-
Direct materials 1,500
Direct labour 5,000
OH based on DL Hrs =750*4 = 3000
---------------------------
Job Cost 9,500 .............>Ans (a)