Apply manufacturing overhead to each of several jobs using both a single overhea
ID: 2373239 • Letter: A
Question
Apply manufacturing overhead to each of several jobs using both a single overhead-rate approach and an activity-based-costing approach, and explain the advantages and disadvantages of the latter, as compared to the former.
Use the following information to answer the following TWO questions:
Acton Company has two products: A and B. The annual production and sales of Product A is 800 units and of Product B is 500 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. The company is considering switching to an activity-based costing system for the purpose of computing unit product costs for external reports. The new activity-based costing system would have three overhead activity cost pools--Activity 1, Activity 2, and General Factory--with estimated overhead costs and expected activity as follows:
1)The predetermined overhead rate under the traditional single-rate costing system is closest to: (Points : 5)
$ 37.46.
$ 21.60.
$ 13.17.
$ 53.68.
2) In correspondence to SLOAT question number 3b.
The overhead cost per unit of Product B under the traditional costing system is closest to: (Points : 5)
$10.74
$7.49
$4.32
$2.63
3) The amount of Activity 1 cost per unit of Product B under the activity based costing system is closest to: (Points : 5)
$24.17
$26.36
$15.82
$29.00
Explanation / Answer
1)The predetermined overhead rate under the traditional single-rate costing system is closest to: (Points : 5)
Ovrehead rate = 102000/1900 = 53.68
$ 53.68.
2) In correspondence to SLOAT question number 3b.
The overhead cost per unit of Product B under the traditional costing system is closest to: (Points : 5)
=(53.68*100)/500 = $10.74
$10.74
3) The amount of Activity 1 cost per unit of Product B under the activity based costing system is closest to: (Points : 5)
=(14500/1100*600)/500unit = 15.82
$15.82