Kolinchak Enterprises has the following production planned for the first quarter of next year:
January 50,000
February 45,000
March 55,000
Each unit requires 3 hours of direct labor time at $10 per hour. Unit-related overhead is $12 per machine hour and each unit requires 1/2 machine hour. Batch-related overhead is $3,000 per batch with a batch-size of 1,000 units. Facility overhead, including depreciation of $17,000, is $59,000 per month. Prepare the direct labor and manufacturing overhead budget for January.
Explanation / Answer
Direct Labor Budget January February March Production Unit 50000 45000 55000 No of Hour Required per unit 3 3 3 Total No of Direct Labor Hour Required 150000 135000 165000 Wage Rate $ 10.00 $ 10.00 $ 10.00 Total Direct Labor $ 1,500,000.00 $ 1,350,000.00 $ 1,650,000.00 Manufacturing Overhead Budget January February March Production Unit 50000 45000 55000 Unit Related Overhead $ 300,000.00 $ 270,000.00 $ 330,000.00 Batch Related Overhead $ 150,000.00 $ 135,000.00 $ 165,000.00 Facility Overhead $ 59,000.00 $ 59,000.00 $ 59,000.00 Total Manufacturing Overhead $ 509,000.00 $ 464,000.00 $ 554,000.00