The following data is given for the stringer Company: Determine the direct mater
ID: 2375397 • Letter: T
Question
The following data is given for the stringer Company:
Determine the direct material quantity variance.
Select the correct answer.
Budgeted production 1,035 units Actual production 916 units Materials: Standard price per ounce $1.83 Standard ounces per completed unit 10 Actual ounces purchased and used in production 8,885 Actual price paid for materials $18,214 Labor: Standard hourly labor rate $15.00 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,717.4 Actual total labor costs $71,940 Overhead: Actual and budgeted fixed overhead $1,107,696 Standard variable overhead rate $26.00 per standard labor hour Actual variable overhead costs $132,087 Overhead is applied on standard labor hours.Explanation / Answer
Hi,
Please find the answer as follows:
Direct Material Qty Variance = Standard Rate*(Actual Material - Standard Material) = 1.83*(8885 - 916*10) = 503 (F)
Option C is correct.
Thanks.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.