What is the amount of variance that is attributed to the difference between the

ID: 2378273 • Letter: W

Question

What is the amount of variance that is attributed to the difference between the budgeted and actual wage rate per hour?
Use the following data to calculate the variances.
The following information has been prepared for a home health agency.


Budgeted costs at actual volume would be $25,344 ($21.12

Budget Actual Wage Rate per Hour $16.00 $17.00 Fixed Hours 320 320 Variable Hours per Relative
            Value Unit (RVU) 1.0 1.1 Relative Value Units (RVUs) 1,000 1,200 Total Labor Hours 1,320 1,640 Labor Costs $21,120 $27,880 Cost per RVU $21.12 $23.23

Explanation / Answer

DL Rate Variance = ( SR ? AR )