Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Landram Corporation makes a product with the following standard costs: In March

ID: 2379758 • Letter: L

Question

Landram Corporation makes a product with the following standard costs:


In March the company produced 4,700 units using 10,160 kilos of the direct material and 2,140 direct labor-hours. During the month, the company purchased 10,730 kilos of the direct material at a cost of $76,610. The actual direct labor cost was $38,252 and the actual variable overhead cost was $11,953.



Inputs Standard Quantity or Hours Standard Price or Rate Direct materials 2.0 kilos $7.00 per kilo Direct labor 1.0 hours $18.00 per hour Variable overhead 1.0 hours $2.00 per hour

Explanation / Answer

Hi,


Please find the answer as follows:


Materials Price Variance = Actual Quantity of Material*(Actual Rate - Standard Rate) = 10730*(76610/10730 - 7) = 1500 (U)



Answer is Option A (1500 U).


Notes:


Actual Rate = Total Cost of Material Purchased/Actual Quantity of Material


Thanks.