Need help in working out this problem pleaseLindsy Company uses activity based costing. The company has two products: A and B. The annual production and sales of Product A is 5000 and of Product B is 2000 units. There are three activity cost pools, with estimated total cost and expected activity as follows:
Activity Cost Pool Estimated Cost Expected Activity A Expected Activity B Total
Act 1 24000 200 800 1000
Act 2 36900 750 150 900
Act 3 63000 1000 800 1800
The cost per unit of product A under activity based costing is closes to
A 14.11
B. 13.77
C. 7
D 17.70
Explanation / Answer
Total Cost/Total activity
Activity level for A
Cost for A
Activity 1
24
200
4,800
Activity 2
41
750
30,750
Activity 3
35
1000
35,000
Total
70,550
Total cost for A is 70,550. Total units for A is 5,000. So unit cost for A is 70,550/5,000 = $14.11
Answer: A, $14.11
Total Cost/Total activity
Activity level for A
Cost for A
Activity 1
24
200
4,800
Activity 2
41
750
30,750
Activity 3
35
1000
35,000
Total
70,550
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.