The following are budgeted data: .............................Sales (units).....
ID: 2385075 • Letter: T
Question
The following are budgeted data:.............................Sales (units).....Production(units)
April.........................12,000..............15,000
May..........................17,000..............16,000
June.........................15,000..............13,000
Each unit requires 0.75 hours of direct labor at a cost of $6.50 per hour. What is the cost of direct labor for May?
a. $73,125 b. $82,875 c. $63,375 d. $78,000
Not sure how to do this, if I figure it by using 17,000 (sales)...then I get answer B, but if I use 16,000 (production)...then I get answer D....how do I know which one to do?
Explanation / Answer
Answer is D. This is because cost of direct labour is always taken on total production done, not on the sales. So, answer is by taking 16,000, i.e part D.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.